Halls & Pickles, Stockport
In July 2016, GLJ completed a 4 week refurbishment of Halls & Pickles Stockport. Our works included installing new doors and frames throughout the canteen, tea points and WC's. GLJ also installed new cubicles, IPS panels, vinyl floors, urinals and sinks to the WCs. GLJ installed Whiterock (Hygienic board) to the canteen, WC & Locker room as well as decorating all other areas which didn’t have whiterock. 
 
GLJ completed the works as per the schedule with minimal disruption to the tenant. G2 Contractors were impressed with our high quality of works. The canteen, tea points and WC's now have a high quality finish as well as looking exceptional.
Client Name: G2 Contractors
Project Value: £35,000